PATNAIK STEEL AND ALLOYS LTD.

Patnaik Steel and Alloys Ltd. has set up one module of 350 TPD Coal based DRI Plant at Keonjhar, Orissa along with 15 MW captive power plant . OSIL Process has been adopted for the proposed plant.

 

OSIL provided the following services: -

- Basic engineering, know-how and training
- Design & engineering of core plant
- Design, engineering & supply of proprietary equipment
- Supervision of erection, testing & commissioning and post commissioning services
- Inspection during manufacturing of core equipment

 

The DRI Plant has been commissioned in May' 2007 and is operating successfully with 99% plant availability.